H2O Innovation은 콜로라도주 클리프턴 수자원구역(Clifton Water District)을 최신화하기 위한 최대규모 한외여과(UF) 프로젝트의 시운전을 완료했다고 발표했다.
이번 한외여과 시스템은 클리프턴 수자원구역에 맞춤으로 설계·제조·시운전됐다. 설계시공된 이 프로젝트는 콜로라도강과 그랜드 밸리(Grand Valley) 운하에서 수집된 급수를 이용해 하루 12MGD(4만5천400㎥)의 식수를 생산할 수 있다.
[원문보기]
H2O Innovation completes Colo. ultrafiltration project
H2O Innovation Inc., a leader in membrane filtration, is proud to announce it completed the commissioning of its largest ultrafiltration (UF) project to date for the Clifton Water District, Colorado.
This ultrafiltration (UF) system was designed, manufactured, and commissioned for the Clifton Water District in Colorado. This design-build project is rated to produce 12 MGD (45,400 m3/day) of potable water with feed water from the Colorado River and the Grand Valley Canal. Aside from the 30 MGD (113,500 m3/day) Montevina, California project currently in its manufacturing phase, Clifton is the largest UF project delivered by the Company to date. “Through this project, H2O Innovation is proving that the open-platform FiberFlexTM, a customer-oriented flexible concept we started promoting in the market place 24 months ago, is indeed a success from a technical and commercial standpoint”, said Denis Guibert - PhD, P. Eng, Vice President Projects and Engineering. To date, H2O Innovation has 15 FiberFlexTM ultrafiltration (UF) facilities being design or in operation, totalling over 55 MGD (208,000 m3/day) of capacity. Of these, four (4) facilities are over 10 MGD (38 MLD) showing that the technical and commercial model developed by the Company for a renewed ultrafiltration market applies to both small and large facilities.
The Clifton facility is treating settled water and includes eight (8) identical UF skids. The design further incorporates constant flow management on the UF system to facilitate control of the pre and post treatment units as well as chemical dosing systems. This project is a retrofit into an existing plant and this created additional engineering challenges. Plant construction had to be scheduled within an operating facility to coincide with the low flow winter months. The project was executed from purchase order to commissioning in less than a year, demonstrating again the ability of H2O Innovation to deliver projects with demanding schedules. “We are pleased to have selected and worked with H2O Innovation. The FiberFlexTM technology integrated perfectly into our complex renovation project and it protects our investment in membrane infrastructure which were key requirements for us. The system and manufacturing quality, project delivery and on-site support have been outstanding”, said Dale Tooker, Manager, Clifton Water District.
The FiberFlexTM racks provide interchangeability and accommodate several types of ultrafiltration modules - similar to spiral wound membrane systems. The use of a FiberFlexTM rack makes changing module suppliers easier and allows the end user to competitively bid these suppliers without having to account for costly infrastructure retrofits that are required for single-module, proprietary UF designs. It also protects the investments made by end users against technical obsolescence and provides much wider upgrade possibilities with more Ultrafiltration membrane modules available to choose from. Endorsed by major membrane manufacturers, H2O Innovation’s approach to a unified rack and ancillary equipment design, the FiberFlexTM system is a long awaited innovation for ultrafiltration systems. The use of FiberFlexTM racks for the Clifton drinking water treatment system differentiated H2O Innovation from other bidders during the OEM selection process.
As H2O Innovation continues to bid and win more ultrafiltration projects, the FiberFlexTM approach is becoming a design basis and requested by more and more consultants and clients. The Clifton project is a great example of H2O Innovation’s ability to take large projects with technological challenges and deliver on its commitments.