| [미국] 헌팅턴 비치 담수화 비용 추정
포세이돈 자료에 따르면, 18만9천m³/D 규모의 캘리포니아 남부 헌팅턴 비치 담수시설의 먹는 물 생산 비용은 US$ 1천424/acre-ft(US$ 1.15/m³)으로 추정된다.
오렌지카운티 수도국(MWDOC, Municipal Water District of Orange County)은 식수의 잠재적인 가격 협상의 윤곽이 나타난 포세이돈 자료의 ‘Water Reliability Agreement Term Sheet’ 초안이 발표될 때인 1월 하순의 물 비용을 인용했다.
[원문보기]
Huntingdon Beach desalination water cost estimated
Poseidon Resources estimates the cost of drinking water produced at its proposed 189,000 m³/d Huntington Beach facility in southern California to be US$ 1,424/acre-ft (US$ 1.15/m³) in January 2013 dollars.
The Municipal Water District of Orange County (MWDOC) quoted the water price at the end of January, when it released Poseidon Resources' draft Water Reliability Agreement Term Sheet that outlines the parameters for negotiating the potential purchase of drinking water.
The figure does not include delivery or conveyance costs, which Poseidon estimates at US$ 94-138/acre-foot (US$ 0.07-0.11/m³). It also presupposes a subsidy of US$ 250/acre-ft (US$ 0.20/m³) from the Metropolitan Water District of Southern California.
The draft term sheet was distributed by Poseidon with a sample letter of intent, which provides a framework for future negotiations and discussions with Poseidon, as well a technical report developed by Richard Brady & Associates outlining water delivery alternatives and related distribution costs. MWDOC and 20 retail water providers are evaluating the potential of purchasing water from the Poseidon facility in a continued effort to enhance water supply reliability within Orange County.
|