[¹Ì±¹] Çظ®½¼Ä«¿îƼ °¡½ºº¹ÇÕȷ¹ßÀü¼Ò ÇÁ·ÎÁ§Æ®, 8¿ù Âø°ø
¢ºProject Name: Harrison County Combined-Cycle Power Plant Project
¢ºOwner: Energy Solutions Consortium and Caithness Energy
¢ºLocation: Harrison County, West Virginia, West Virginia, USA
¢ºCapacity: 630 MW
¢ºAmount: U$ 700 Mill.
¢ºStatus:
-Following several years of planning, the developers hope to begin construction in Aug. 2019.
-The developers are still in negotiations with an EPC contractor.
-Developers are aiming for an estimated in-service date of November 2021.
¹Ì±¹ ¿¡³ÊÁö¼Ö·ç¼Ç ÄÁ¼Ò½Ã¾ö(Energy Solutions Consortium)°ú ÄÉÀ̽º³×½º¿¡³ÊÁö(Caithness Energy)°¡ °øµ¿À¸·Î ÃßÁøÇÏ´Â Çظ®½¼Ä«¿îƼ °¡½ºº¹ÇÕȷ¹ßÀü¼Ò ÇÁ·ÎÁ§Æ®ÀÇ °Ç¼³°ø»ç°¡ ¿À´Â 8¿ù¿¡ ½ÃÀÛµÉ ¿¹Á¤ÀÌ´Ù. ÀÌ ÇÁ·ÎÁ§Æ®´Â 630MW±Þ °¡½ºº¹ÇÕȷ¹ßÀü¼Ò¸¦ ¿þ½ºÆ® ¹öÁö´Ï¾ÆÀÇ Çظ®½¼Ä«¿îƼ¿¡ °Ç¼³ÇÏ´Â 7¾ï ´Þ·¯ ±Ô¸ðÀÇ »ç¾÷ÀÌ´Ù. ÇöÀç EPC¾÷ü ¼±Á¤À» À§ÇÑ Çù»óÀÌ ÁøÇà ÁßÀ̸ç, º»°ø»ç ±â°£Àº 24°³¿ù·Î 2021³â 11¿ù ÁØ°øÀ» ¸ñÇ¥·Î ÇÏ°í ÀÖ´Ù.
[Ãâó = Á¶¼ºÈ¯ÀÇ Ç÷£Æ®°Ç¼³ À̾߱â(http://blog.daum.net/sungwhan_c) / 2019³â 4¿ù 13ÀÏ]
|